Archive for November, 2007
Construction
Posted in Progress on November 10, 2007| Leave a Comment »
Day 39 – Finishing touches
Posted in Progress on November 10, 2007| Leave a Comment »
Day 33 – Nearly there… a few teasers
Posted in Progress on November 5, 2007| Leave a Comment »
Day 32 – Plants and Monoliths
Posted in Progress on November 4, 2007| Leave a Comment »
Jonny breaches the cordon and enters the mud free zone to do yet more digging..
…to make a base for this slate monolith…
…plants arrive on site…
…some more tyres are painted blue to make waves…
…and the blue boat in lined to make it into a planter.
Day 31 – Mud Free Zone
Posted in Progress on November 3, 2007| Leave a Comment »
A trip to the world of timber…
…and a big pile of timber…
…is transformed…
…into planting boxes…
…and giant pencils…
…pink floyd boat is painted red…
…the tyre wall gets a hose down and is finished off with purple slate chippings…
…the patio is washed and scrubbed…
…and declared a mud free zone in preparation for painting.
Day 30 – Tyred
Posted in Progress on November 1, 2007| Leave a Comment »
The second course is laid…
…and the hardcore goes in behind…
…Adam makes waves…
… and the third course of tyres with loose topsoil and compost for planting goes on top of the tyre wall.